In CW04-2012 IMR continued to invest in workplace safety
In CW04-2012 IMR continued to invest in workplace safety. 20 extra men of the operational staff in theory and practice have been trained, tested and certified with the support of our partner GARDEMANN according to the IPAF guidelines as a lifting platform operator. Scissors and swivel arm manlifts (so called “cherry pickers”) are used in many areas and involve numerous risks. Through the observance of basic operating instructions, most hazards are reduced to virtually zero. Emergency lowering and other maneuvers were practiced by each participant which gives confidence in dealing with the devices.
IMR rebranded!

IMR rebranded! We see ourselves as piping specialists in northern Germany. Since for our customers we have long been known as "IMR from Hamburg" and as a now European wide operating company we wanted to strengthen our brand recognition with a name than can more easily be remembered from non German speaking people and still be present for our old customers. Therefore we are now working under the name "IMR HAMBURG GmbH" for you. On the 23rd of June 2011 the new company name was already registered in the commercial register of Hamburg with the number HRB 85504. Of course we are still accessible as usual with the existing telephone numbers, email and postal addresses. Also banking details remain unchanged.
Safety at work initiative 2011
In CW06-2011 the entire personal employed in the new building on CFPP Wilhelmshaven by IMR operational personal and executive staff where trained and tested in accordance with SCC Doc. 18 and 17. As a campaign for safe, healthy and environmentally sound work aims IMR in continuous improvement under this years motto of our BG (work insurance) “Stop Accidents”.
Big step towards HP done!
In CW50-2010 efforts to continuous improvement and development of IMR’s welding technology culminated after several processes checks and reference annealing now in the successful and timely completion of the first "P92" weld in manual TIG/E process within the new coal fired power plant Wilhelmshaven for Electrabel Gas de France Suez with the dimensions of outer diameter 570 x wall thickness 75 [mm ]. Figure 1 shows one of our HD-welder at important measuring of the pipes inner misalignment.
IP LP piping package Rotterdam ordered
In December, 2009 the order was given to IMR for manufacturing and erection of IP, LP and partial HP piping systems of the project „New building of KW Rotterdam Electrabel EBL2 “. The customer Hitachi Power Europe GmbH (HPE) from Duisburg builds there essential components of the new 800 MW coal power plant for the belgian energy provider Electrabel.
P92 WPQ with wall thickness range over 120mm
In the competition as a system supplier for assembly and welding technology of e.g. fresh steam pipes and turbine connections strives the IMR further at the head in the processing of the material X 10 CrWMoV 9-2 (material number 1.4901). The long winter was used to weld together in January 2010 pipes from the so-called "P92" material with the dimensions 330x64.
IP LP piping package Wilhelmshaven ordered
In December, 2009 the order was given to IMR for manufacturing and erection of IP, LP and partial HP piping systems of the project „New building of KW Wilhelmshaven Electrabel W1“. The customer Hitachi Power Europe GmbH (HPE) from Duisburg builds there essential components of the new 800 MW coal power plant for the belgian energy provider Electrabel.
SmartPlant Isometrics and PiCoDa launched
October 2009: In Cooperation with Hitachi Power Europe GmbH IMR has successfully introduced different Software-Solutions from the Piping Solution of Intergraph PP&M Germany GmbH. With the help of SmartPlant Isometrics based on the ISOGEN-Standard 80 KKS within small bore piping have allready been designed.
Auditing of Procedures “P92” successfully completed
In May 2009 auditing of procedures Rohr 33,7x8.0mm and 396*30mm for the material X 10 CrWMoV 9-2 material- Nr. 1.4901 were tested through weld verification as well as NDT (company Pockrandt www.pockrandt-tqs.de) and through destructive testing (Germanischer Llyod Prüflabor, Herne).
Fluidcon Walsum10
In June 2009 in the construction of Block 10 of Walsum thermal power station, workings on the pulverize fuel ash management were incorporated with workings on fluidization management. Besides prefabricated spools, the welds for assembling were carried out as adaptations at the locality.